Subansiri Lower Hydro-Electric Project

mins read
3

Table of Contents

Subansiri Lower Hydro-Electric Project

Sources: Arunachal Times

Date: 4/12/2025

Syllabus: GS 1, GS 3

Why in the news?

250 MW Unit-2 of the Subansiri Lower Hydro-Electric Project has been successfully test-synchronised with the national grid on 2 December 2025. Commercial power supply is to begin within December 2025.

Subansiri Lower Hydro-Electric Project

Current Progress:

  • Unit-1 and Unit-2 completed underwater mechanical run on 24 October and 6 November.
  • Three units (Unit-1, Unit-2, Unit-3/4) expected to add 1000 MW generation after commissioning.
  • Four more units will be commissioned between 2026 – 27.
  • Completing all eight units will significantly enhance regional energy supply.

What are the Significances?

  • Hydropower Potential in Arunachal Pradesh:
    • The state has India’s highest hydropower potential (~50,000 MW).
    • SLHEP is among the largest hydro projects in NE India.
    • Critical for regional development, electrification, and employment.
    • Strengthens India’s renewable energy capacity.
    • Upon completion, it will add approx. 7.421 billion units (BU) of renewable energy annually once fully operational.
  • Inter-State Importance: Arunachal Pradesh & Assam:
    • Helps stabilize power supply in Assam.
    • Helps reduce peak shortages in the Northeast grid.
    • Infrastructure cooperation model between hill state (Arunachal) and plains state (Assam).
  • Environmental & Social Dimensions:
    • Run-of-river project → relatively lower submergence.
    • Reduces fossil-fuel dependence; enhances grid stability in NE India.
    • Supports India’s long-term goal of carbon neutrality.
  • Economic Impact:
    • Provides clean, low-cost electricity.
    • Reduces power import burden for NE states.
    • Creates direct and indirect employment in construction, transport, services.
    • Boost for industrial demand and economic growth in Arunachal Pradesh and Assam.
  • Strategic Importance:
    • Hydropower development in Arunachal strengthens India’s presence in a border region near China.
    • Supports strategic infrastructure and energy security.

Aspirants can strengthen GS-1 and GS-3 preparation through expert guidance at UPSC & APSC Coaching in Guwahati.

What are the key Concerns?

  • River flow regulation of Subansiri.
  • Flood concerns downstream in Assam.
  • Siltation and impact on fisheries.

Important Fact:

  • Subansiri River is a tributary of the Brahmaputra.
  • SLHEP capacity: 2000 MW.
  • Current unit commissioned: Unit-2 (250 MW).
  • Executing agency: NHPC.
  • Type: Run-of-river hydroelectric project.
  • States involved: Arunachal Pradesh & Assam.

Mains Practice Question:

Q. Discuss the significance of the Subansiri Lower Hydroelectric Project (SLHEP) for India’s renewable energy transition and regional development. Highlight the environmental and inter-state concerns associated with the project.

Pointers for Answer:

Introduction

  • 2000 MW run-of-river project on Subansiri River (tributary of Brahmaputra).
  • Unit-2 (250 MW) test-synchronised with national grid in Dec 2025.

Significance for Renewable Energy

  • Arunachal Pradesh has the highest hydropower potential (~50,000 MW).
  • SLHEP is one of largest hydro projects in Northeast India.
  • Will generate ~7.421 BU renewable power annually when fully operational.
  • Supports India’s clean energy targets & reduces fossil-fuel dependence.
  • Enhances grid stability in the NE region.

Regional Development Impact

  • Strengthens power availability in Arunachal Pradesh & Assam.
  • Reduces peak shortages in the Northeast grid.
  • Boosts local employment, infrastructure, and industrial growth.
  • Enhances rural electrification and economic linkages.

Inter-State Importance

  • Cooperative model between hill state (Arunachal) & plains state (Assam).
  • Helps address chronic power deficits in Assam.
  • Improves inter-state connectivity and power-sharing mechanisms.

Strategic Importance

  • Hydropower development strengthens India’s presence in border areas near China.
  • Supports strategic infrastructure and long-term energy security.

Environmental & Social Concerns

  • Downstream flood risks in Assam due to flow regulation.
  • Siltation issues affecting river ecology and fisheries.
  • Impacts on Subansiri basin hydrology and community livelihoods.
  • Need for robust dam safety audits and sustainable flow management.

Way Forward

  • Strengthen downstream impact assessment and monitoring.
  • Adopt silt-management technologies & ecological flow norms.
  • Improve inter-state coordination mechanisms.
  • Ensure community participation and transparent rehabilitation measures.

Regular answer writing using Civil Services Mains Practice Question improves analytical clarity and structuring for GS answers.

UPSC EPFO result 2025 out. SPM IAS Academy
Featured
The Union Public Service Commission (UPSC) has officially declared the UPSC EPFO Result 2025 for
Featured
Use the UPSC photo resizer online tool below to resize photo for UPSC, compress to
Featured
Score in the optional paper can make a significant impact on your UPSC CSE Mains
IAS vs IPS Officer_ Key Differences in Roles, Responsibilities, and Salary in Indian Governance
Featured
When it comes to the civil services in India, the two most prestigious and sought-after
upsc-admit-card
Featured
UPSC Prelims Admit Card 2025 Released: The Union Public Service Commission (UPSC) has officially released
UPSC CSE 2024 Service Allocation List Out – Check IAS, IPS, IFS Allotment
Featured
The much-awaited UPSC CSE 2024 Service Allocation List has officially been released. After months of
Call Now